  1. The applicant shall submit FORM-P along with an application addressed to the Director, Directorate of Fire and Emergency Services, St. Inez, Panaji – Goa for the issue of Initial No Objection Certificate. PDF icon(Click to view) (212 KB) English
  2. The applicant shall submit the Documents to Establish the Right over the property.
  3. The applicant shall submit One set of Architectural Plans (Blueprint Only) consisting of Site Plan, Elevation Plan, Section Plan & all Floor Plans, duly approved by Town & Country Planning Department or Planning & Development Authority.
  4. The applicant shall submit One set of Fire Protection Plans indicating the Fire Prevention, Life Safety  & Fire Protection measures along with relevant documents ( Site Plan, Floor wise Plan, Elevation Plan & Section Plan) that are proposed to be incorporated in the building as per National Building Code of India 2005 (Part 4 – Fire & Life Safety), The Goa (Regulation of Land Development & Building Construction) Act, 2008 and The Goa Land Development and Building Construction Regulation, 2010 (Read with clause Annexure III, Additional Fire Prevention and Life Safety Requirement) & the Notification 3/5/97/HD(G) Part/3934, dated 17/12/2014 issued by Government of Goa and as amended from time to time.
  5. Scrutiny of the documents of Step 1 to 4 and further consultation with the Owner & Architect/Consultants if required.
  6. Inspection of the site and issue of recommendations.
  7. Party submits the Undertaking on Rs. 50/- stamp paper in Form-U to abide by the Fire Prevention, Life Safety, and Fire Protection Measures recommended to carry out the Fire Prevention Life Safety, and Fire Protection recommended at Step No. 6. PDF icon(Click to view) (138 KB) English
  8. The issue of Initial No Objection Certificate.
  9. The applicant shall submit FORM-F along with an application addressed to the Director, Directorate of Fire and Emergency Services, St. Inez, Panaji – Goa for the issue of Final No Objection Certificate. PDF icon(Click to view) (210 KB) English
  10. Final inspection of the premises for physical verification & testing of Active & Passive and Fire Protection measures installed as per Initial No Objection Certificate. 
  11. The issue of Memorandum for payment of Licence fee @ Rs.10/-perSq.mtr.of the built-up area as per Notification No. 3/7/85-HD(G/Vol.II), dated 18/05/2010 and as amended from time to time.
  12. Payment for No Objection Certificate fee of Rs.150/- as per Notification No. 3/7/85-HD(G/Vol.II), dated 18/05/2010 and as amended from time to time.
  13. The issue of Final No Objection Certificate.

Note:- The Final No Objection Certificate issued shall be renewed annually. 